A bid falls two years short on support
Compare the promised support with the required operating time.
MAINTENANCE
EVIDENCE
Starting position and test order
A fictitious public procurement agency plans to operate networked technology monitors for seven years from 2028. The pre-documented criteria require a confirmed supply during this time, a reachable security contact point and the reconstructable assignment of an updated component for the version offered.
The offer confirms the conformity documents for the version offered. Contact point and component sample are successfully confirmed in the sample. The manufacturer documents five years of support. A reliable contractual commitment for the last two planned years is missing. The purchasing team keeps the criterion open in its evaluation.
Compare test data and consequences
Operation and maintenance
- Scale
- 7 years confirmed
- Observation
- 5 years
- Follow
- 2 years remain open
Safety contact and component reference
- Scale
- Both samples can be traced
- Observation
- 2 out of 2 occupied
- Follow
- Secure existing partial proofs
Assessment per version
- Scale
- Originals and commitment to the tender
- Observation
- Product proofs are available, care commitment remains open
- Follow
- The criteria are not considered to be fulfilled
Two years of care stay open
Secure the duration, version and promised performance before the awarding legal assessment.
Edit the test step by step
Determine requirements and conditions of proof before evaluation
Link the use, required duration, product acquisition and required safety evidence with the documented assessment basis.
Testable evidence Reasoned criteria and verifiable scale per offer.
- Acceptance criterion
- Trace the decision to the agreed requirement and observed result. Assign an owner and review date to open conditions.
- Evidence
- Decision record with requirement, result, evidence references, approval status and dates for open items.
Practically compare explanation, care and contact
Arrange the documented delivery stand. Check contact response and an example proof of a well-kept component. Compare the confirmed period with the deployment plan.
Testable evidence Comparison matrix with observed results and concretely open care time.
- Acceptance criterion
- A second reviewer can follow the statement to the original evidence and the version checked. Record the evidence identifier or file reference with the decision.
- Evidence
- Evidence list recording original source, version, documented mapping and owner.
Document deviation and operator sequence
Keep track of your own assessment status and the clarification permitted by the award rules. Arrange additional operational evidence required for the responsible role.
Testable evidence Dated decision with gap, location and further processing.
- Acceptance criterion
- A second reviewer can follow the statement to the original evidence and the version checked. Record the evidence identifier or file reference with the decision.
- Evidence
- Evidence list recording original source, version, documented mapping and owner.
Worked decision and negative test
Decision in case
The product documents and the two sample samples are positively documented. Two years of care are missing for the own evaluation criterion. The contracting authority clarifies according to the relevant procedural rules whether and how the gap can be answered
A five-year commitment alone does not decide on the CRA conformity or award. The responsible body evaluates confirmed deployment, individually relevant support obligation and own requirements based on the evidence.
Counter-sample and impact
Complete an indeterminate statement "Support can be extended in principle" from a sales presentation. Check the liability, version and concrete duration. Without corresponding proof, the comparison level remains at five years.
- Audit record
- Comparison of the original finding and retest showing the changed condition, observed effect and closure decision.
Templates and worksheets
Award criteria, manufacturer maintenance and operating time
Compare the required operating time and practical manufacturer's proofs with the specific offer.
Outcome Comparable procurement documents with gaps in evidence and actual product status.
Read the instructions
Fictional example Seven years of operation are required, and care is confirmed for five years.
- Identify the starting situation Recognise needs, wording and criteria from the procurement basis
- Run the test Compare support commitment, product documentation and observable care.
- Secure decision and evidence ensure deviation and allow for clarification in the procurement file.
Official sources
First check for this task
Cyberresilience Regulation in text
Use the article or attachment that regulates the task to be solved.
Responsibility of manufacturers of digital products
Compare preparation, product release and care with your own manufacturer role.
NIS2 Directive on supply chain security and coordinated risk assessments
For a regulated buyer, in particular Article 21 and the relevant assessments under Article 22 shall be relevant.
Other official references1
- DORA: Management of the third party ICT risk (opens in new tab)
EUR-Lex · Verordnung (EU) 2022/2554
Arrange service, affected function, contractual obligations and alternative options to the specific customer.
What depends on your result?
Procuring with product proof
Transfer the same test criteria to your own product and save the different starting data.
Checking evidence of procurementCheck direct suppliers at the required performance
Arrange the confirmed product data for a recorded institution of your own supplier and risk assessment.
Work through the caseCheck the supplier before ordering
For a DORA-relevant ICT service, you will also determine the financial function, the service provider and the appropriate contract documents.
View the guideSupport period and security updates
Check the actual manufacturer's justification of the support period and the accessibility of updates.
Check support and updates