Prepare threat-led testing
Clear the validity and responsibilities.
APPLY
DOCUMENT
Clear the mandate, responsibilities and clearances for a TLPT
Check that the financial entity has been selected by the competent authority for a threat-oriented penetration test. For further testing, combine the relevant requirements, agreements with external stakeholders and the process of completion and resolution.
The preparation begins with the question of which company and the scope of the inspection is covered. Set out the professional functions, third-party services involved and the interface for supervision in a file. Name the responsible roles for protecting the operation, release and confidential handling of the results.
The supervisory, audit and clearance shall be agreed
Determine the relevant official decision and the critical or important functions to be examined.
Document application decision and supervisory contact
Determine the entity, competent authority, selection reference and relevant functions. Check which confirmation is required for the planned scope of the examination.
- Acceptance criterion
- A second reviewer can follow the statement to the original evidence and the version checked. Record the evidence identifier or file reference with the decision.
- Evidence
A comprehensible decision on the relevant test path.
Establishing test responsibility and business protection
Document the professional goals, roles, independence, secure communication and escalation paths. Set clearances with the responsible authorities and the conditions for interruption and completion.
- Acceptance criterion
- Trace execution, review and approval to named roles. Check handover and deputy arrangements in the exercise.
- Evidence
An approved organisational framework with responsible persons and communication channels.
Prepare for completion and resolution
Plan the closing meeting, the retention of evidence and the follow-up to agreed measures. Link the final receipt with the competent supervisor and internal recipients.
- Acceptance criterion
- Use the same metric, population and unit for expected and observed results. Record the measurement point at which the business service is achieved.
- Evidence
A tracking plan with prioritized findings and clearance.
Secure the statement with a sample
Check whether an external dependence in the extent released, the escalation plan and the contractual participation rules have been taken into account.
- Acceptance criterion
- Reconcile the approved scope with the identified external dependency, participation arrangements and escalation chain. Treat unresolved responsibilities as an approval item.
- Evidence
- Agreement reconciliation linking the service, current clause, operating evidence and decision on any discrepancy.
A service provider contributes to the tested function
The bank identifies an external dependence in payment transactions. The responsible parties clarify the scope, permissible participation and responsibility prior to the order release. The contractual possibility of cooperation is documented in the release file.
Documented order and closing process Classification, released scope, roles, final report and follow-up of measures can be found together.
- What you are examining
- Compare documented supervisory communication, the approved scope of testing and the contractually confirmed contribution of the ICT service provider. Check which technical function is included and who gives the release.
- What the post-test decides
- Follow an pending consent to the competent body. The test file must indicate which decision is to be taken and what amendment needs to be approved again.
- Audit record
- Agreement reconciliation linking the service, current clause, operating evidence and decision on any discrepancy.
Legal basis for this task
Compare the decision from the test example with the relevant rule.
Articles 26 and 27 DORA and Delegated Regulation (EU) 2025/1190 · Test procedures
The relevant authorities are the selection of authorities, the requirements for implementation and testers and the phases described in the standard.
For your exam Classification, released scope, roles, final report and follow-up of measures can be found together.
To classify the applicable test plan
Deriving a test program from critical functions, failure scenarios and open findings and proving its coverage. For internal evaluation, the assessments on EUGRC.AI are available.