NIS2 · LEGAL SOURCES

NIS2 legal register

Find provisions in Germany’s BSIG, the NIS2 Directive and sector-specific rules, with checks for each task.

SCOPE
IMPLEMENTATION
EVIDENCE

Which legal area answers the question?

For German institutions, the BSIG is in the foreground with plants and sectoral rules. The directive assigns national obligations, rights and the European framework. The implementing regulation concreteises the work scale for explicitly mentioned digital providers.

NIS2 · Standards Register

Art. 8 DVO (EU) 2024/2690 · Considerability of data centre services

Addressee Types of providers and their services explicitly identified

Arrange the monitoring to the data centre service concerned, its relevant facilities and the appropriate criterion for service or data impairment.

Measures, evidence and sampling

Art. 8NIS2-DV08-001

Secure data centre service and infrastructure access

Arrange the service and impact to the actually affected facilities and alternatives of the article.

Testable evidence
Building and service, technical measurement and impact report.
Sample
Distinguishing a regional failure in the environment from the unavailability of the commissioned data centre service.

Point (a) to (d)NIS2-DIG-005

Check data centre service according to its own criteria

Check full unavailability, limited availability of more than one hour, maliciously caused data impairment and impaired physical access separately.

Testable evidence
Observations per data centre service with documented operating system and access access.
Sample
Compare a complete failure of 30 minutes with a limited operation of 60 minutes. The evaluation must show different alternatives.

Supervision instructions and interpretation

Editorial guidanceNIS2-FAQ-DIG1

What does a full failure of exactly 30 minutes mean for the cloud and data centre?

Art. 7(a) requires more than 30 minutes of complete unavailability in cloud. Art. 8(a) does not provide for a minimum duration when the data centre service is completely out of service. Further alternatives and exceptions are to be assessed per service.

For your exam Apply the duration of the case to both separate services. Secure your own decision per service.

Related provisions

Other official references1

Editorial update 2026-11-28 · Fassung und Zuständigkeit für den eigenen Stichtag prüfen.

Acts and official implementing aids

First check for this task

Other official references1

Checking or preparing your own proof

State of change

A change in the legal situation is to be included in the audit order.

Trace the amendment, the date it applies and the affected workflow as of the same cut-off date.

Work result The amendment note shows when and how it was reviewed.

Templates and worksheets

They want to collect their own data and capture a verifiable result.

Use calculated work aids to process classification, implementation, reporting deadlines and evidence.