What you decide and prove

Start with the approved type, the scope covered and the conditions specified in the certificate. Make the planned change and its effect on the requirements for the product status in question comprehensible.

For module B, the manufacturer shall inform the relevant notified body of any changes that may affect the conformity or conditions of the certificate. Check whether additional approval is required and refer to the modified type.

The EU type examination and subsequent conformity with the module C type prove different steps. For the new delivery, place both required documents in the same file and track actual production.

Edit the test step by step

  1. Determine the scope of the original certificate

    Compare version, risks, conditions and functions affected by the new situation.

    Testable evidence A verified description of the change with a clearly defined scope.

    Acceptance criterion
    Justify applicability using evidenced activity or intended use, role and date. Assign an owner and due date to any unresolved assumption.
    Evidence
    Reasoned applicability assessment recording facts, reference, role, date and open assumptions.
  2. The required approval will lead to the target

    Secure the notification, material and response of the competent authority. Determine a necessary supplement separately.

    Testable evidence The additional approval is comprehensible.

    Acceptance criterion
    Trace the decision to the agreed requirement and observed result. Assign an owner and review date to open conditions.
    Evidence
    Decision record with requirement, result, evidence references, approval status and dates for open items.
  3. Connect tested type and actual series produced

    Arrange the confirmed version to the production documents. Capture which units represent the actual approved status.

    Testable evidence Release decision per delivery stand with supporting documents for modules B and C.

    Acceptance criterion
    The item under review and the documents refer to the same approved version. Record obsolete evidence as a separate discrepancy.
    Evidence
    Versioned mapping of item, source and approved version with any discrepancy recorded.

The internal report is correct, the certificate does not yet record the new status

A manufacturer of a fictitious Class I product uses the way out of Module B and C in his case. For Version 5.0, there is a certificate. With Version 5.1, the team changes the module for testing update release.

For version 5.1, all agreed internal scenarios are fulfilled after the test. The change may affect the approved conditions and has already been notified to the competent body. Additional approval confirmed for 5.1 is not yet available at the time of the exercise.

What you'll find out in the case

A comprehensible decision to change with the correct certification and production reference.

Editing the Practice Case

Templates and worksheets

  • Standard coverage and type level

    Track standard reference, actual application, procedural gap and confirmed scope of the type.

    Outcome Evidence per requirement and release status of the appropriate assessment method.

    Read the instructions

    Fictional example Six out of nine requirements are covered by the approved standard version.

    1. Identify the starting situation Confirm the official basis and actual edition.
    2. Run the test assess coverage and the necessary complementary procedure.
    3. Secure decision and evidence Check the certificate and the actual delivered stand.

Official sources

What depends on your result?

  • Ensure conformity in series production

    Check whether the documented delivery actually depicts the confirmed type.